Changing Perceptions and Practices in the Slums of Dhaka, Bangladesh

DSK, Water 1st’s partner organization in Bangladesh, sent in a great story with their most recent quarterly report. In the Tarabo Hatipara neighborhood of the sprawling Demra slum, the common practice by local contractors has been to sink drinking water wells to a depth of 90 – 130 feet. Wells at that depth aren’t always free of pollutants (like arsenic) or deep enough to produce consistently during the dry season. For those reasons, Water 1st’s partner DSK set its own standard years ago that requires all wells to be at least 200 feet deep.

img_5511-compressed

Contractors hand-drilling a well in Kamrangir Char slum of Dhaka, Bangladesh, a neighborhood too densely populated to bring in a drilling rig.

The challenge is that the contractors who actually install the DSK wells are not always convinced that it is necessary to go down to 200 feet. When the community hires a contractor to install the well, the contractors frequently try to convince the community to save a little money and just dig down to about 120 feet. The communities are responsible for repaying the cost of constructing the well, so they are often interested in minimizing the construction costs, sometimes to the detriment of the long term performance of the well.

So DSK took two steps to solve this ongoing problem. First they went into the community and talked to residents about the benefits of digging deeper wells. While the community members were receptive to the messages, they had a difficult time committing to the extra expense of drilling more than 200 feet. They found one woman, Moyna Begum, who was willing to give it a try. When they completed Moyna Begum’s 240-foot deep well, they invited the neighbors over to her compound to see the results for themselves. They tried the water and noticed a difference. After the visit to Moyna Begum’s place, four groups decided to proceed with their own deep wells.

img_0510-compressed

Water 1st's Steve Deem (left) discusses construction of water systems with Akhtar Jahan (center), the civil engineer in DSK's Pallabi slum office, along with Ranajit Das, DSK project manager, in December 2009.

The other approach that DSK pursued was with the contractors themselves. DSK organized a training for well drillers at which they discussed all the strategies for constructing a protected drinking-water well. Thirty-four contractors attended the training and improved their knowledge base in the practice of installing wells. Now the contractors have a better understanding of the reasons behind all the standards DSK has established for the drinking wells installed through their program. This has reduced the amount of conflicting information that the community members receive as they embark upon the important venture of installing their own domestic water supply.

We think this story demonstrates the importance of working through a strong local partner organization. The issue of shallow wells arose during our site visit in December 2009. We noted a few examples of wells that were less than 200 feet deep. DSK was with us and we discussed it as an issue at our wrap-up meeting. We left it to them to figure out what was happening and how to correct it. Six months later, DSK had done the research on the problem and developed a solution that would address it at the demand-side (community members) and the supply-side (contractors). This characterizes our relationship with DSK over years and demonstrates why they are a trusted and valued partner in this endeavor.

Construction isn’t just for the men!

Construction on the large Las Minas, Honduras project is well underway.  This large water system will benefit four communities and 700 people.  When we visited in April, construction of the spring cap and sand trap was nearly complete.   The community members had also extended extended the 4.5 mile long transmission pipeline from the mountain spring water source within a quarter mile of the first community’s storage tank.

Macana Carcamo, a grandmother from the community of Valle de la Cruz, is participating in the construction work for her community's new water project.

Macana Carcamo, a grandmother from the community of Valle de la Cruz, is participating in the construction work for her community's new water project.

Macana Carcamo, a grandmother pictured above, is proud of her contribution to the construction of the Las Minas project.  So far she has worked 37 days on the project, watering the concrete pylons that support the transmission pipeline while they are curing. 

Read more about our visit to Las Minas and see some of our photos here.