July 2025 Kokelo and Nyatigo Project Update

Water1st’s local partner, KWAHO, is leading the development of two separate piped water systems serving the communities of Kokelo and Nyatigo. Kokelo: Expanding Household Connections Since January 2025, community members in Kokelo have contributed significant labor to complete the water system. Volunteer crews installed the final sections of pipeline, bringing every household within reach of […]

July 2025 Emukoye Project Update

CABDA continues to expand the Emukoye project, extending service to additional villages. As of January 2025: 101 water connections completed in Phase 1 of the project (primarily in Emukoye village), 119 connections completed in Phase 2 (primarily in Musango and Mulwanda) As of June 2025: An additional 50 connections completed in Musango and Mulwanda Total […]