At the time of our September visit, 19 households were receiving daily service from Kokelo’s water supply system, far short of the 148 connections that were scheduled to be completed by now. To connect the remaining 129 households, the community must complete 3 critical sections of water supply pipe. This is the first project of its kind in the area, which means there will be implementation challenges as the details of the program get established. In most Water1st projects, it’s the responsibility of the community to dig trenches and backfill them. This is not always the case with development projects, which led to speculation that funds had been dispersed to pay for the trenching. However, we were able to clarify the situation during our visit and trenching is progressing well now.
There had been progress in other parts of the project at the time of our visit. Crews have completed most of the work on the toilets for Magwako Primary School. The structures have been built and fixtures were being installed during our visit. The septic pit for all 3 toilet blocks (a girls’ block, a boys’ block, and a teachers’ block) was excavated and the structural features were being poured. The water committee opened an office, where community members can make payments or register for a service connection. People who have water service are very pleased with the water and their new toilets and showers. The water committee is developing strategies to mobilize the community to complete the final sections of water supply pipeline.